    PM FPX 5333 Assessment 2 Earned Value Analysis Report

    Earned Value Management (EVM) is an important project management technique used to evaluate project progress, monitor spending, identify schedule delays, and forecast final costs. The Earned Value Analysis of NearlyFree.com’s New Employee Orientation (NEO) project reveals significant cost and schedule performance problems that require immediate management attention. Although the project has completed approximately 43% of its planned work, actual expenditures exceed the budgeted value of completed activities, and progress is substantially behind schedule.

    NearlyFree.com is developing an automated, web-based employee training system designed to simplify new employee orientation, reduce administrative responsibilities, and minimize the staff time required to train new employees. However, the project has encountered financial and scheduling challenges that could affect its successful completion. The original project plan established a 92-day timeline and an approved budget of $22,300, although another project description identifies an initial budget of $25,000. This discrepancy must be resolved to ensure accurate financial reporting.

    PM FPX 5333 Assessment 2 Earned Value Analysis Report

    The current Earned Value Management calculations show an Earned Value (EV) of $12,373.95, a Planned Value (PV) of $20,453.95, and an Actual Cost (AC) of $16,373.95. These figures produce a negative cost variance of $4,000 and a negative schedule variance of $8,080. The Cost Performance Index (CPI) is approximately 0.76, while the Schedule Performance Index (SPI) is approximately 0.61. If the current cost efficiency continues, the estimated final project cost will reach approximately $29,505.90, exceeding the stated $22,300 budget baseline.

    This PM FPX 5333 Assessment 2 report examines the Earned Value Management methodology, calculates key project performance indicators, evaluates the projected final cost, and recommends corrective actions. The goal is to help NearlyFree.com improve project control, address existing inefficiencies, and complete its employee orientation system successfully.

    Overview of the NearlyFree.com NEO Project

    NearlyFree.com is implementing a New Employee Orientation (NEO) system to improve how new employees receive training and become familiar with organizational procedures. The proposed solution is an automated, web-based platform that will centralize training materials, reduce repetitive administrative tasks, and make orientation more efficient.

    The project is intended to minimize the time employees and managers spend conducting manual training activities. By automating important orientation processes, the organization expects to improve consistency, simplify access to training resources, and reduce the operational burden associated with onboarding new employees.

    The project was initially planned for completion within 92 days, with a stated approved budget of $22,300. However, the project documentation also identifies an initial budget of $25,000. Management should verify which amount represents the authorized Budget at Completion (BAC) before finalizing project forecasts.

    The project manager must evaluate performance using several measures, including completed scope, schedule adherence, actual expenditures, resource utilization, and expected business benefits. Earned Value Management provides a structured approach for bringing these measures together.

    Understanding Earned Value Management in Project Management

    Earned Value Management is a project control methodology that integrates scope, schedule, and cost information to measure how effectively a project is progressing against its approved plan. It helps project managers determine whether completed work is consistent with the time and financial resources allocated to the project.

    Unlike traditional budget monitoring, which focuses primarily on how much money has been spent, EVM compares the budgeted value of completed work with the value of work scheduled and the actual expenditure incurred.

    This comparison allows project managers to identify problems before they become more difficult or expensive to correct. It also supports forecasting by estimating the likely final cost based on current project performance (Peng, 2018; Haughey, 2020).

    For NearlyFree.com, Earned Value Analysis provides a way to evaluate the development of the NEO platform, determine why spending is exceeding the value of completed work, and establish whether the remaining project activities can be completed within the original financial and scheduling expectations.

    Key Components of Earned Value Analysis

    Three primary measurements form the foundation of Earned Value Management: Earned Value, Planned Value, and Actual Cost.

    Earned Value (EV) represents the budgeted value of the work that has actually been completed by the reporting date. It measures project progress according to the original cost baseline rather than the amount of money spent.

    Planned Value (PV) represents the budgeted value of the work that should have been completed by the reporting date. It provides a reference point for determining whether the project is progressing according to its original schedule.

    Actual Cost (AC) represents the total amount spent on the work completed by the reporting date. It includes the actual financial resources consumed during project execution.

    The original project documentation may also use the traditional terms Budgeted Cost of Work Performed (BCWP), Budgeted Cost of Work Scheduled (BCWS), and Actual Cost of Work Performed (ACWP). These correspond to EV, PV, and AC, respectively.

    Current Earned Value Data for NearlyFree.com

    The following figures provide the foundation for evaluating the NEO project’s financial and scheduling performance.

    Performance measureAmount
    Earned Value (EV)$12,373.95
    Planned Value (PV)$20,453.95
    Actual Cost (AC)$16,373.95
    Budget at Completion (BAC)$22,300.00

    The figures indicate that the project has completed less work than originally scheduled while spending more than the budgeted value of the work delivered. This combination suggests that the project is experiencing both schedule delays and unfavorable cost performance.

    The following calculations provide a more detailed understanding of these performance issues.

    Schedule Variance Analysis for the NEO Project

    Schedule Variance (SV) measures the difference between the budgeted value of completed work and the budgeted value of work scheduled by the reporting date. It helps project managers determine whether project progress is ahead of or behind the original plan.

    The formula for Schedule Variance is:

    [SV = EV – PV]

    Using the NearlyFree.com project figures:

    [SV = $12,373.95 – $20,453.95]

    [SV = -$8,080]

    <badge color=”danger”>Negative schedule variance</badge>

    The project has a Schedule Variance of -$8,080, indicating that the value of completed work is significantly below the value of work that was scheduled. This suggests that the NEO development team is experiencing delays in completing planned activities.

    The project manager should investigate the reasons for this performance gap. Potential causes include incomplete development tasks, technical dependencies, insufficient staffing, unclear requirements, and delays in testing or approval activities.

    It is important to understand that schedule variance is expressed in budgeted monetary units rather than calendar days. Therefore, the negative $8,080 result indicates a performance shortfall but does not establish the exact number of days the project is behind schedule.

    Cost Variance Analysis for the NEO Project

    Cost Variance (CV) compares the budgeted value of completed work with the actual amount spent to complete that work. It helps determine whether the project is using its financial resources efficiently.

    The formula for Cost Variance is:

    [CV = EV – AC]

    Using the project data:

    [CV = $12,373.95 – $16,373.95]

    [CV = -$4,000]

    <badge color=”danger”>Negative cost variance</badge>

    The negative Cost Variance of $4,000 indicates that NearlyFree.com has spent $4,000 more than the budgeted value of the work completed. This represents unfavorable financial performance and suggests that project activities are costing more than originally planned.

    Several factors could contribute to this situation, including underestimated labor requirements, technical difficulties, additional development work, inefficient resource utilization, or repeated corrections to completed tasks.

    Management should review project expenditures and identify the activities responsible for the overrun. Corrective measures should focus on improving productivity, controlling unnecessary expenses, and managing remaining resources without compromising the functionality or quality of the NEO system.

    Schedule Performance Index (SPI) Analysis

    The Schedule Performance Index measures how efficiently the project is progressing compared with its planned schedule. It represents the relationship between the budgeted value of completed work and the budgeted value of scheduled work.

    The formula is:

    [SPI = \frac{EV}{PV}]

    Using the NearlyFree.com figures:

    [SPI = \frac{$12,373.95}{$20,453.95}]

    [SPI \approx 0.605]

    <badge color=”danger”>SPI: 0.61</badge>

    The Schedule Performance Index of approximately 0.61 indicates that the project is earning about 61 cents of budgeted work value for every dollar of work value scheduled.

    An SPI below 1.00 indicates that the project is behind schedule. In this case, the result highlights a substantial difference between planned and actual progress.

    The project manager should review unfinished activities, identify critical dependencies, evaluate employee availability, and determine which tasks are delaying completion. A realistic recovery schedule should then be developed to address the remaining work and establish achievable milestones.

    Cost Performance Index (CPI) Analysis

    The Cost Performance Index evaluates how efficiently the project uses its financial resources. It compares the budgeted value of completed work with the actual amount spent.

    The formula is:

    [CPI = \frac{EV}{AC}]

    For NearlyFree.com:

    [CPI = \frac{$12,373.95}{$16,373.95}]

    [CPI \approx 0.756]

    <badge color=”danger”>CPI: 0.76</badge>

    The Cost Performance Index of approximately 0.76 indicates that the project is earning about 76 cents of budgeted work value for every dollar spent.

    Because the CPI is below 1.00, the project is experiencing unfavorable cost efficiency. If the same performance continues, the organization may need additional funding to complete the remaining development activities.

    Management should investigate the causes of inefficient spending and evaluate whether labor allocation, development procedures, technical requirements, or rework are contributing to the problem. Improving cost efficiency should remain a priority throughout the remaining project phases.

    Budget at Completion (BAC)

    Budget at Completion represents the total approved budget allocated to complete a project. It serves as the financial baseline for measuring spending and estimating the final project cost.

    For the NearlyFree.com NEO project, the stated Budget at Completion is:

    [BAC = $22,300]

    However, the project description also identifies an initial budget of $25,000. This difference creates a potential reporting issue that should be resolved before the final cost forecast is approved.

    Management should confirm whether $22,300 represents the formally authorized project baseline and whether $25,000 was an earlier estimate, an initial funding limit, or a separate financial allocation.

    Establishing the correct baseline is essential because all earned value calculations and financial forecasts depend on accurate project budget information.

    Estimate at Completion (EAC) Analysis

    Estimate at Completion forecasts the total amount of money expected to be spent by the time the project is finished. It considers the actual costs incurred and the expected cost efficiency of the remaining work.

    When current cost performance is expected to continue, the following formula is appropriate:

    [EAC = AC + \frac{BAC-EV}{CPI}]

    Using the NearlyFree.com project figures:

    [EAC = $16,373.95 +
    \frac{$22,300-$12,373.95}
    {0.75577}]

    [EAC \approx $29,505.90]

    The estimated final cost is approximately $29,505.90 if the project’s current cost efficiency continues.

    This forecast exceeds the approved $22,300 budget by approximately $7,205.90, representing a projected cost increase of approximately 32.3%.

    The calculation uses the unrounded CPI to maintain accuracy. Using a rounded CPI of 0.76 produces a slightly different result.

    EAC should be treated as a forecast rather than a guaranteed final expenditure. As project conditions change, management should update the estimate using new information about remaining activities, resource requirements, technical challenges, and the effectiveness of corrective actions.

    Summary of Earned Value Analysis Results

    The following table summarizes the primary performance indicators for the NearlyFree.com NEO project.

    EVM indicatorResultInterpretation
    Earned Value (EV)$12,373.95Budgeted value of completed work
    Planned Value (PV)$20,453.95Budgeted value of scheduled work
    Actual Cost (AC)$16,373.95Actual expenditure
    Cost Variance (CV)-$4,000Spending exceeds earned value
    Schedule Variance (SV)-$8,080Project is behind planned progress
    Cost Performance Index (CPI)0.76Unfavorable cost efficiency
    Schedule Performance Index (SPI)0.61Unfavorable schedule performance
    Budget at Completion (BAC)$22,300Stated approved budget
    Estimate at Completion (EAC)$29,505.90Forecast final project cost

    The results demonstrate that the project requires corrective action in both financial management and schedule control. The negative variances and performance indices below 1.00 indicate that the original project plan is no longer an accurate reflection of current performance.

    Project Turnaround Strategies and Corrective Actions

    The Earned Value Analysis identifies several areas that NearlyFree.com must address to improve the likelihood of successful project completion. The organization should develop a structured recovery plan that focuses on the causes of poor performance rather than simply extending the deadline or increasing the budget.

    Reassess the Project Schedule and Remaining Activities

    The project manager should review the work breakdown structure and evaluate the remaining development activities. Each unfinished task should be examined to determine its estimated duration, resource requirements, dependencies, and potential risks.

    Particular attention should be given to activities that affect the project’s critical path. Identifying these activities can help management prioritize work that directly influences the final completion date.

    An updated schedule should include realistic milestones, clear task ownership, and regular progress reviews. The revised completion date should reflect the actual amount of remaining work rather than an arbitrary deadline extension.

    Strengthen Cost Management and Budget Control

    Management should investigate why actual expenditure exceeds the budgeted value of completed work. This review should include labor expenses, technical rework, resource allocation, development inefficiencies, and unexpected project requirements.

    The project manager should also prepare a revised estimate of the remaining work to determine whether additional funding is necessary. Any proposed budget increase should include supporting calculations, a clear explanation of the cost drivers, and formal stakeholder approval.

    Cost control should not mean eliminating essential activities. Instead, the organization should focus on reducing unnecessary expenses, improving resource utilization, and ensuring that spending contributes directly to the project’s approved objectives.

    Improve Project Monitoring and Performance Reporting

    NearlyFree.com should establish a consistent project monitoring process that tracks Earned Value, Planned Value, Actual Cost, CPI, and SPI at regular intervals.

    These indicators should be reviewed alongside information about completed deliverables, unresolved technical issues, resource availability, and emerging risks.

    Regular performance reports can help management identify negative trends before they become more serious. They also provide an objective basis for evaluating whether corrective actions are producing measurable improvements.

    Prioritize Essential Requirements and Maintain Quality

    The project team should review the NEO system’s requirements and distinguish between essential functionality and optional enhancements. Features that are not critical to the initial release may be considered for a later development phase, provided the changes receive appropriate stakeholder approval.

    However, reducing scope should not compromise essential system functionality, security, usability, or employee training requirements.

    Testing and quality assurance must remain part of the implementation process. Rushing development by skipping essential testing may create defects that lead to additional expenses and undermine the intended benefits of the automated orientation platform.

    Improve Stakeholder Communication and Accountability

    Effective communication is essential when a project experiences significant cost and schedule challenges. The project manager should provide stakeholders with regular updates about spending, progress, risks, and proposed recovery actions.

    Reports should clearly explain the difference between the approved budget and the projected final cost. They should also identify decisions that require management approval and assign responsibility for resolving outstanding issues.

    Transparent communication can help maintain stakeholder confidence, improve accountability, and ensure that everyone understands the project’s current position and revised expectations.

    Conclusion

    The Earned Value Management analysis of NearlyFree.com’s New Employee Orientation project identifies significant challenges involving cost efficiency and schedule performance. The project has earned $12,373.95 in budgeted work value while incurring $16,373.95 in actual costs, resulting in a negative cost variance of $4,000 and a negative schedule variance of $8,080.

    The Schedule Performance Index of approximately 0.61 indicates that the project is progressing behind its original schedule, while the Cost Performance Index of approximately 0.76 demonstrates unfavorable cost efficiency. Assuming current cost performance continues, the estimated final project cost is approximately $29,505.90, exceeding the stated $22,300 budget baseline.

    To improve project performance, NearlyFree.com should reassess unfinished activities, investigate cost overruns, establish a realistic recovery schedule, strengthen financial monitoring, and improve stakeholder communication. Any proposed budget or schedule changes should be supported by documented analysis and formal approval.

    By applying Earned Value Management consistently and implementing targeted corrective actions, the organization can improve project visibility, manage remaining resources more effectively, and increase the likelihood of completing the automated employee orientation system successfully.

    Frequently Asked Questions (FAQs)

    1. What is PM FPX 5333 Assessment 2 about?

    PM FPX 5333 Assessment 2 focuses on using Earned Value Management to evaluate the performance of NearlyFree.com’s New Employee Orientation project. It examines cost and schedule variances, performance indices, estimated final costs, and corrective actions needed to improve project performance.

    2. What is Earned Value Management in project management?

    Earned Value Management is a project control technique that combines scope, schedule, and cost information to measure project performance. It helps managers determine whether completed work is progressing according to the approved budget and schedule.

    3. What is the current financial status of the NearlyFree.com NEO project?

    The project has an Earned Value of $12,373.95 and an Actual Cost of $16,373.95. This creates a negative Cost Variance of $4,000, indicating that the organization has spent more than the budgeted value of the work completed.

    4. What does a negative Schedule Variance mean?

    A negative Schedule Variance means that the project has completed less work than was originally planned by the reporting date. NearlyFree.com’s negative Schedule Variance of $8,080 indicates a significant gap between planned and actual progress.

    5. What does a Cost Performance Index of 0.76 indicate?

    A CPI of 0.76 means that the project is earning approximately 76 cents of budgeted work value for every dollar spent. This indicates unfavorable cost performance and suggests that the project is using financial resources less efficiently than planned.

    6. What does a Schedule Performance Index of 0.61 mean?

    An SPI of 0.61 indicates that the project has earned approximately 61 cents of budgeted work value for every dollar of scheduled work value. Because the result is below 1.00, the project is behind its planned schedule.

    7. What is the estimated final cost of the NearlyFree.com project?

    Using the stated Budget at Completion of $22,300 and assuming current cost efficiency continues, the estimated final cost is approximately $29,505.90. This represents a projected overrun of approximately $7,205.90.

    8. How can NearlyFree.com improve its project performance?

    The organization can improve performance by reassessing unfinished activities, investigating cost overruns, improving resource allocation, establishing realistic milestones, monitoring EVM indicators, and maintaining transparent communication with stakeholders.

    9. Why is Earned Value Analysis important for project managers?

    Earned Value Analysis provides measurable information about project progress, financial efficiency, and schedule performance. It helps project managers identify problems early, forecast final costs, evaluate corrective actions, and make informed decisions about project resources.

    10. What is the difference between Earned Value and Actual Cost?

    Earned Value represents the budgeted value of work completed, while Actual Cost represents the money actually spent to complete that work. Comparing these two measurements helps determine whether the project is spending more or less than planned for its completed activities.

    References

    Cullen, S. (2016, August 2). Earned value analysis. Whole Building Design Guide. https://www.wbdg.org/resources/earned-value-analysis

    Haughey, D. (2020, July 26). What is earned value? Project Smart. https://www.projectsmart.co.uk/what-is-earned-value.php

    Peng, B. (2018, April 10). The earned value method. ProjectEngineer. https://www.projectengineer.net/the-earned-value-method/

    Usmani, F. (2020, August 18). Planned value (PV), earned value (EV), and actual cost (AC) in project cost management. PM Study Circle. https://pmstudycircle.com/2012/05/planned-value-pv-earned-valueev-actual-cost-ac-analysis-in-project-cost-management-2/