PM FPX 5334 Assessment 2 Bausch + Lomb Project
Earned Value Management (EVM) is an essential project management technique for evaluating whether a project is meeting its planned schedule, budget, and performance objectives. In the NearlyFree.com New Employee Orientation (NEO) training system project, the current performance indicators reveal significant schedule delays and unfavorable cost performance. Based on the reported figures, the project has an Earned Value (EV) of $12,373.95, a Schedule Performance Index (SPI) of approximately 0.60, and a Cost Performance Index (CPI) of approximately 0.76. These results indicate that the project is behind schedule and spending more than expected to complete its work.
NearlyFree.com initially approved a project budget of $22,300 and a planned duration of 92 days. However, the project has experienced cost overruns and slower-than-expected progress. Management has requested an evaluation of the project’s current financial and scheduling performance, along with recommendations for bringing the initiative back under control.
This PM FPX 5334 Assessment 2 report applies Earned Value Analysis to evaluate project performance, calculate important cost and schedule indicators, forecast the final project expenditure, and recommend corrective actions. It also examines inconsistencies in the available project information that should be resolved before management approves a revised budget or timeline.
Overview of the NearlyFree.com NEO Training System Project
The primary objective of the NearlyFree.com project is to develop and implement an automated, web-based New Employee Orientation (NEO) training system. The proposed platform is intended to simplify the employee onboarding process by providing a centralized and consistent approach to orientation and training.
Currently, employee orientation activities require personnel resources to coordinate training information, communicate requirements, and guide new employees through onboarding procedures. Automating these activities is expected to reduce administrative workload, improve training consistency, and minimize the time employees spend managing routine orientation tasks.
The project was approved with a total budget of $22,300 and a planned completion period of 92 days. Its success depends on completing the required system functionality, managing implementation costs, meeting the established timeline, and ensuring that the final platform supports the organization’s onboarding requirements.
Because the project is experiencing unfavorable performance, management needs a clear understanding of the current situation before making decisions about additional funding, resource allocation, or schedule adjustments.
Understanding Earned Value Management in Project Management
Earned Value Management is a project control methodology that combines scope, schedule, and cost information to evaluate project performance. It compares the value of completed work with the value of work planned and the actual amount spent.
Unlike a traditional financial review that focuses primarily on money spent, EVM evaluates whether expenditures are producing the expected amount of completed work. This allows project managers to identify situations in which a project is spending too much, progressing too slowly, or experiencing both problems simultaneously.
According to the Project Management Institute (PMI, 2017), Earned Value Management provides a structured approach to measuring project performance against an approved baseline. It also supports forecasting, allowing managers to estimate the resources and funding required to complete remaining activities.
For NearlyFree.com, EVM is particularly useful because the project has experienced both schedule delays and cost overruns. Evaluating these factors together provides a more complete picture of project health and helps management determine the appropriate recovery strategy.
Key Components of Earned Value Analysis
Three primary measurements are required to perform an Earned Value Analysis: Earned Value, Planned Value, and Actual Cost.
Earned Value (EV) represents the budgeted value of work that has actually been completed by a specific reporting date. It is calculated by multiplying the approved budget for each activity or work package by its completion percentage and then combining the results.
Planned Value (PV) represents the budgeted value of the work that should have been completed by the reporting date according to the approved project schedule.
Actual Cost (AC) represents the amount of money actually spent to complete the work performed during the reporting period.
The original project documentation also uses the traditional terms Budgeted Cost of Work Performed (BCWP), Budgeted Cost of Work Scheduled (BCWS), and Actual Cost of Work Performed (ACWP). These correspond to EV, PV, and AC, respectively.
The reported financial information for NearlyFree.com is presented below.
| Earned Value component | Reported amount |
|---|---|
| Earned Value (EV/BCWP) | $12,373.95 |
| Planned Value (PV/BCWS) | $20,453.95 |
| Actual Cost (AC/ACWP) | $16,373.95 |
| Budget at Completion (BAC) | $22,300.00 |
These figures provide the foundation for calculating the project’s schedule performance, cost efficiency, and estimated final expenditure.
Earned Value Analysis Calculations for NearlyFree.com
The project manager can use several EVM formulas to determine whether the NEO training system is progressing according to its original plan. The most important calculations include Schedule Variance, Cost Variance, Schedule Performance Index, and Cost Performance Index.
Schedule Variance (SV)
Schedule Variance measures the difference between the budgeted value of completed work and the budgeted value of work scheduled by the reporting date.
The formula is:
[SV = EV – PV]
Using NearlyFree.com’s project figures:
[SV = $12,373.95 – $20,453.95]
[SV = -$8,080.00]
The Schedule Variance is -$8,080, indicating that the project has completed less work than originally planned. The negative result means that the budgeted value of completed activities is $8,080 below the value of activities that should have been completed by the reporting date.
This finding highlights a significant scheduling problem. Management should investigate delayed activities, resource availability, technical dependencies, and potential workflow interruptions.
It is important to understand that Schedule Variance is expressed in monetary terms rather than days. Therefore, the negative result does not indicate that the project is exactly $8,080 worth of days behind schedule. A revised project schedule is necessary to determine the actual delay in calendar days.
Cost Variance (CV)
Cost Variance measures whether the completed work is costing more or less than originally budgeted.
The formula is:
[CV = EV – AC]
For NearlyFree.com:
[CV = $12,373.95 – $16,373.95]
[CV = -$4,000.00]
The Cost Variance is -$4,000, indicating that the organization has spent $4,000 more than the budgeted value of the work completed.
This unfavorable result suggests that the project is experiencing cost inefficiencies. Potential causes include inaccurate cost estimates, inefficient resource utilization, unexpected technical problems, additional development work, or repeated corrections.
A negative Cost Variance does not mean that the entire project budget has been exhausted. Instead, it shows that the work completed so far has cost more than its approved budgeted value. If this trend continues, the final project expenditure may significantly exceed the original allocation.
Schedule Performance Index (SPI)
The Schedule Performance Index measures the efficiency of project progress by comparing Earned Value with Planned Value.
The formula is:
[SPI = \frac{EV}{PV}]
Using the available figures:
[SPI = \frac{$12,373.95}{$20,453.95}]
[SPI \approx 0.60]
NearlyFree.com’s Schedule Performance Index is approximately 0.60. This means that the project is completing approximately $0.60 worth of budgeted work for every $1.00 worth of work planned by the reporting date.
An SPI below 1 indicates that the project is behind schedule. An SPI of 1 represents performance consistent with the approved schedule, while an SPI above 1 indicates that more work has been completed than planned.
The current result demonstrates that project progress is significantly slower than expected. Management should review the project schedule, identify activities affecting the critical path, and determine whether additional resources or changes to task sequencing could improve performance.
Cost Performance Index (CPI)
The Cost Performance Index measures how efficiently the project uses its financial resources.
The formula is:
[CPI = \frac{EV}{AC}]
For NearlyFree.com:
[CPI = \frac{$12,373.95}{$16,373.95}]
[CPI \approx 0.76]
The Cost Performance Index is approximately 0.76, meaning the project is generating about $0.76 in budgeted work value for every dollar spent.
A CPI below 1 indicates unfavorable cost performance. In this case, NearlyFree.com is spending more than planned to complete its activities.
This result suggests that management should investigate the reasons behind the increased expenditure. Reviewing labor costs, technical requirements, resource assignments, development processes, and rework may help identify opportunities to improve cost efficiency.
Budget at Completion (BAC)
Budget at Completion represents the total approved budget for completing all project activities. It serves as the financial baseline against which actual spending and future cost forecasts are evaluated.
For NearlyFree.com, the original Budget at Completion is:
[BAC = $22,300]
This amount represents the initial approved funding for developing and implementing the automated NEO training system.
Although the original budget remains the project’s financial baseline, the unfavorable CPI indicates that the organization may need additional funding to complete the remaining work. Management should therefore evaluate the current performance trends instead of assuming that the original budget will be sufficient.
Estimate at Completion (EAC)
Estimate at Completion forecasts the total project expenditure based on actual costs and the expected cost of completing the remaining work.
When the current cost performance is expected to continue, the following formula can be used:
[EAC = AC + \frac{BAC-EV}{CPI}]
For NearlyFree.com, the calculation begins by identifying the remaining budgeted value of work:
[BAC-EV = $22,300-$12,373.95]
[= $9,926.05]
Using the unrounded CPI calculated from the original figures:
[EAC = $16,373.95 +
\frac{$9,926.05}{0.7557}]
[EAC \approx $29,505]
The estimated final project cost is therefore approximately $29,505, assuming that the current cost efficiency continues throughout the remaining work.
This forecast suggests that the project could exceed its original $22,300 budget by approximately $7,205, representing an increase of about 32.3%.
The EAC is a forecast rather than a confirmed final expenditure. Actual results may differ if management improves productivity, reduces unnecessary expenses, changes the remaining scope, or introduces more efficient implementation methods.
Summary of Earned Value Management Results
The following table summarizes the major EVM calculations for the NearlyFree.com NEO training system project.
| Performance measure | Result | Interpretation |
|---|---|---|
| Earned Value (EV) | $12,373.95 | Budgeted value of completed work |
| Planned Value (PV) | $20,453.95 | Budgeted value of scheduled work |
| Actual Cost (AC) | $16,373.95 | Actual project expenditure |
| Schedule Variance (SV) | -$8,080.00 | Unfavorable schedule performance |
| Cost Variance (CV) | -$4,000.00 | Unfavorable cost performance |
| Schedule Performance Index (SPI) | 0.60 | Project is behind schedule |
| Cost Performance Index (CPI) | 0.76 | Project is over budget relative to completed work |
| Budget at Completion (BAC) | $22,300.00 | Original approved budget |
| Estimate at Completion (EAC) | Approximately $29,505 | Forecast final project expenditure |
The results confirm that the project is experiencing both schedule delays and cost inefficiencies. The negative Schedule Variance and SPI below 1 indicate that less work has been completed than planned. Similarly, the negative Cost Variance and CPI below 1 demonstrate that the organization is spending more than expected to produce the completed work.
These findings suggest that the original project estimates, resource allocation strategy, or monitoring procedures may require revision. Management should conduct a detailed review of the Work Breakdown Structure, task dependencies, resource assignments, and financial assumptions before approving a recovery plan.
Project Budget Recovery and Turnaround Strategy
The Earned Value Analysis indicates that NearlyFree.com needs a structured recovery strategy to improve project performance. Continuing with the existing approach without addressing the underlying problems could result in additional delays and higher costs.
The objective should not simply be to extend the project deadline or increase the available budget. Instead, management should identify the reasons behind the unfavorable performance indicators and implement corrective measures that improve both schedule efficiency and cost control.
Reassess the Original Project Schedule
The first recovery step should involve reviewing the original 92-day project schedule and comparing planned activities with actual progress.
The project manager should identify delayed tasks, incomplete deliverables, resource constraints, and dependencies that are preventing other activities from moving forward. Particular attention should be given to activities on the critical path because delays in these tasks can directly affect the project’s completion date.
A revised schedule should include realistic task durations, updated milestones, clear responsibilities, and an accurate critical path. Where appropriate, activities may be reorganized or completed in parallel, provided that the changes do not introduce additional risks or reduce system quality.
Review the Project Budget and Remaining Costs
The projected EAC of approximately $29,505 indicates that the original $22,300 budget may not be sufficient to complete the project under current performance conditions.
Management should review all remaining activities, outstanding financial commitments, labor requirements, and anticipated technical expenses. This review should distinguish between essential costs, avoidable expenses, rework, and optional system enhancements.
If additional funding is necessary, the project manager should prepare a formal justification explaining the expected cost increase, its business value, available alternatives, and the consequences of not approving additional resources.
This approach will help management make informed financial decisions while maintaining accountability for project expenditures.
Improve Resource Allocation and Cost Control
Inefficient resource utilization can contribute to increased project costs and delayed deliverables. NearlyFree.com should evaluate whether the existing team has the appropriate technical skills, workload distribution, and resources to complete the remaining activities.
Project managers should review employee assignments, labor expenses, development processes, and task completion rates. Responsibilities should be clearly defined to reduce duplicated work and unnecessary delays.
Regular cost reviews should compare actual expenditures with the budgeted value of completed work. This will help management recognize unfavorable spending patterns and take corrective action before additional costs accumulate.
Additional employees or overtime may be considered when justified, but management should evaluate their financial impact and expected contribution before approving these measures.
Establish Consistent Project Performance Monitoring
NearlyFree.com should introduce a structured performance monitoring process that tracks Earned Value, Planned Value, Actual Cost, Schedule Variance, Cost Variance, SPI, and CPI.
During the recovery phase, weekly progress reports may provide management with sufficient visibility into important performance changes. Reports should identify major variances, explain their causes, document corrective actions, and provide updated forecasts for project cost and completion.
Clear escalation procedures should also be established. Significant schedule delays or unfavorable cost trends should be communicated to senior management promptly so that decisions can be made before problems become more difficult to resolve.
Strengthen Project Scope Management
Uncontrolled scope changes can increase development complexity, extend implementation schedules, and create additional financial requirements.
The project manager should ensure that all proposed changes are formally evaluated before approval. Each change should be assessed according to its effect on project scope, schedule, budget, technical requirements, and expected business benefits.
Nonessential features may be postponed to a future release if doing so does not compromise the essential requirements of the NEO training system. The immediate priority should be delivering a functional and reliable platform that meets the organization’s core employee onboarding needs.
Reconcile Project Completion and Earned Value Figures
Another important issue involves the reported project completion percentage. The original information states that the project is approximately 43% complete. However, the reported Earned Value of $12,373.95 represents approximately 55.5% of the original $22,300 budget.
These figures may be based on different measurement methods. For example, the 43% figure may represent a physical completion estimate, while Earned Value reflects the budget-weighted value of completed work.
If both percentages are intended to represent the same overall completion measure, the information is inconsistent and should be corrected.
The project manager should verify how the completion percentage was calculated and ensure that task progress, Earned Value measurements, and schedule reporting follow consistent rules. Accurate data is essential before management makes decisions about additional funding, revised deadlines, or project recovery.
Key Project Management Lessons Learned
The NearlyFree.com NEO project demonstrates why effective planning, resource management, and continuous performance monitoring are essential for successful project delivery.
One important lesson is that project estimates must reflect the actual complexity of the work. Initial budgets and schedules should account for technical requirements, employee availability, testing activities, dependencies, and possible implementation risks.
Another lesson is that project managers should monitor performance throughout the implementation process rather than waiting until major problems develop. Regular EVM reporting can help identify unfavorable cost and schedule trends early, allowing corrective actions to be introduced before the situation becomes more serious.
The project also highlights the importance of understanding the causes of poor performance. Increasing the budget or extending the deadline does not automatically resolve inefficiencies. Management must investigate whether delays result from resource limitations, unrealistic estimates, technical difficulties, scope changes, or ineffective workflows.
Finally, reliable project reporting requires accurate and consistent information. Reconciling completion percentages and verifying financial data can improve forecasting and support better management decisions.
Conclusion
The NearlyFree.com New Employee Orientation training system project is experiencing significant schedule delays and unfavorable cost performance. Earned Value Analysis shows a Schedule Variance of -$8,080, a Cost Variance of -$4,000, an SPI of approximately 0.60, and a CPI of approximately 0.76. These results indicate that the project is progressing more slowly and costing more than originally planned.
The estimated final project cost is approximately $29,505, compared with the original approved budget of $22,300. This forecast highlights the need for a structured recovery strategy that addresses scheduling problems, cost inefficiencies, resource allocation, and scope management.
NearlyFree.com should reassess its project schedule, review remaining costs, improve resource utilization, strengthen performance monitoring, and control unnecessary scope changes. Management should also reconcile the reported 43% completion figure with the Earned Value calculations to ensure that future decisions are based on consistent information.
By applying Earned Value Management and implementing targeted corrective actions, the organization can improve project visibility, manage financial risks, and increase the likelihood of successfully delivering its automated employee orientation system.
Frequently Asked Questions (FAQs)
1. What is PM FPX 5334 Assessment 2 about?
PM FPX 5334 Assessment 2 focuses on evaluating the performance of the NearlyFree.com New Employee Orientation training system project using Earned Value Management. It examines project costs, schedule performance, financial forecasts, and corrective actions needed to improve project outcomes.
2. What is Earned Value Analysis in project management?
Earned Value Analysis is a project management technique that compares the budgeted value of completed work with planned work and actual expenditures. It helps project managers evaluate whether a project is meeting its schedule and budget expectations.
3. Is the NearlyFree.com NEO project behind schedule?
Yes. The project has a Schedule Variance of -$8,080 and a Schedule Performance Index of approximately 0.60. These results indicate that the project has completed less budgeted work than originally planned by the reporting date.
4. Is the NearlyFree.com project over budget?
The project is experiencing unfavorable cost performance. Its Cost Variance is -$4,000, indicating that completed work has cost $4,000 more than its budgeted value. The estimated final cost is approximately $29,505 if the current cost efficiency continues.
5. What does a Cost Performance Index of 0.76 indicate?
A CPI of 0.76 means that the project is producing approximately $0.76 in budgeted work value for every dollar spent. Since the value is below 1, the project is experiencing cost inefficiency.
6. What does a Schedule Performance Index of 0.60 mean?
An SPI of 0.60 indicates that the project is completing approximately 60% of the budgeted work value planned by the reporting date. It demonstrates unfavorable schedule performance but does not directly represent the number of days the project is delayed.
7. How is Estimate at Completion calculated?
When current cost performance is expected to continue, the EAC formula is:
[EAC = AC + \frac{BAC-EV}{CPI}]
For NearlyFree.com, the calculation produces an estimated final project cost of approximately $29,505 using the unrounded CPI.
8. How can NearlyFree.com reduce project cost overruns?
The organization can improve cost performance by reviewing remaining activities, identifying inefficient processes, improving resource allocation, monitoring expenditures regularly, and controlling unnecessary scope changes. Management should also update financial forecasts and approve additional funding only when justified.
9. Why is project schedule monitoring important?
Schedule monitoring helps identify delayed activities, resource constraints, task dependencies, and potential risks before they affect the overall completion date. Regular reviews allow project managers to revise timelines and introduce corrective measures when necessary.
10. What is the difference between Earned Value and Actual Cost?
Earned Value represents the budgeted value of the work completed, while Actual Cost represents the money spent to complete that work. Comparing these two figures helps determine whether a project is completing its activities within the expected cost.
11. Why is Earned Value Management important for project recovery?
EVM provides measurable information about project performance and helps management identify cost and schedule problems. It also supports financial forecasting, corrective planning, and informed decisions about resources, deadlines, and project priorities.
References
Haughey, D. (2020, July 26). What is earned value? Project Smart. https://www.projectsmart.co.uk/what-is-earned-value.php
Peng, B. (2018, April 10). The earned value method. Project Engineer. https://www.projectengineer.net/the-earned-value-method/
Project Management Institute. (2017). A guide to the project management body of knowledge (PMBOK® guide) (6th ed.). Project Management Institute. https://www.pmi.org/pmbok-guide-standards/foundational/pmbok
Usmani, F. (2020, August 18). Planned value (PV), earned value (EV), and actual cost (AC) in project cost management. PM Study Circle. https://pmstudycircle.com/2012/05/planned-value-pv-earned-valueev-actual-cost-ac-analysis-in-project-cost-management-2/
Cullen, S. (2016, August 2). Earned value analysis. Whole Building Design Guide. https://www.wbdg.org/resources/earned-value-analysis